Commissioner Mike Cantrell
District 2
Town of Highland Park

Beverly Drive
(Town of Highland Park)
Last updated Summer 2013

Lead Agency:
Town of Highland Park

Description:
The entire project is from Westside Drive to Airline Road

Cost and Funding:
The total cost of the project is $3,603,700 with Dallas County contributing $1,000,000 and the Town funding the remainder of the project.

Current Status:
Although most of the project has been completed, there is still a section UNDER CONSTRUCTION at this time.

Preston Road
(Town of Highland Park)
Last updated Spring 2016

Lead Agency:
Town of Highland Park

Description:
Reconstruct Preston Road from Armstrong to St. Andrews. Upgrades include drainage improvements, asphalt overlay or reconstruction, new or improved traffic lights, and repaired sidewalks.

Cost and Funding:
The total cost of the project is $3,061,380 with Dallas County and Highland Park each contributing $1,530,690.

Current Status:
The Agreement between Dallas County and the Town of Highland Park was approved in May 2016.